Detail:
HCM Street Project (Nam Can – Dat Mui, Ca Mau province)
General Information:
HCM Street is vital route in Vietnam. Parts are in progress, about 3.167 km long. HCMC Street is also the second one from North to South, crossing Western mountainous area, along with 1A National Road, locates mostly in Eastern Coastal Delta.
This route has being built on the basis of upgrading and expanding countryside roads and national roads. Parts on the basis of available roads are called segment of national road/countryside road.
On December 3rd, 2004, 6th meeting, XI, National Assembly of Vietnam has enforced Document 38/2004/QH11 of construction and investment undertaking of HCM street, confirmed it as vital nationwide project.
Main Route of HCM Street runs across following locations:
Pác Bó, Cao Bằng town , Bắc Kạn town , Chợ Mới, Bắc Kạn, Chu Market, Muồng Pass , Trung Sơn intersection , Phú Thịnh intersection , Bình Ca bridge (sông Lô), Km124+500 National Road 2, intersection Phú Hộ, town Phú Thọ, bridge Ngọc Tháp (sông Hồng), Cổ Tiết, Trung Hà bridge , Sơn Tây town , Hòa Lạc, Xuân Mai, Chợ Bến, Xóm Kho, Ngọc Lặc, Lâm La, Thái Hòa Town , Tân Kỳ, Khe Cò, Phố Châu, Vũ Quang, Tân Ấp, Khe Gát, Bùng, Cam Lộ, bridge Tuần, Khe Tre, Đê Bay pass, Mũi Trâu pass , Túy Loan, Hòa Khương, Thạnh Mỹ, Lò Xo pass , Ngọc Hồi, Kon Tum, PleiKu city, Buôn Ma Thuột city, Gia Nghĩa, Chơn Thành, Bình Phước intersection, Đức Huệ, Thạnh Hóa, Tân Thạnh, Mỹ An, Cao Lãnhcity , Cao lãnh bridge (sông Tiền), Vàm Cống bridge (sông Hậu), Rạch Sỏi, Minh Lương, Gò Quao, Vĩnh Thuận, Cà Mau city, Đầm Cùng bridge, Năm Căn, Đất Mũi.
Capital Source : in form of BT, BOT, ODA and government bonds.
Design Scale of Package 19 : Trại Niệm bridge construction
- Bridge Type : pre-stressed concrete bridge
- Length : L=156.22m
- Bridge spans : including 5 bridge spans, each of 24.54m
- Life : 100 years;
- Design load: HL93, accounting with alone heavy means XB-80, pedestrian load: 300KG/m2;
- Bridge Transaction : 9m (car lane: 7m, balcony 2x0.5m, safety zone: 2x0.5m);
- Linking road transaction: road surface 8m long + strengthened border 2x1.0=2m;
- Earthquake Load: Level 5;
Duration: 24 months
Contract Value : ……billion VND
Design Scale of Package 22 : Kenh Nam bridge – Kenh Ho Bridge:
- Bridge Type : Bridge pre-stressed concrete bridge;
- Length : L=156.22m
- Bridge spans : 6 spans 24.54m (Kenh Nam); 7 spans (Kenh Ho);
- Life : 100 years;
- Design Load : HL93, accounting with alone heavy means XB-80, pedestrian load 300KG/m2;
- Transaction bridge : 9m (car lane: 7m, balcony 2x0.5m, safety zone: 2x0.5m);
- Linking road transaction : road surface 8m long + strengthened border 2x1.0=2m;
- Earthquake load: Level 5;
Duration: 24 months
Contract Value : ……billion VND
Design Scale of Package 41 : Kinh Nam bridge
- Bridge Type : Bridge pre-stressed concrete bridge;
- Length : L=180.83m
- Bridge spans : 7 spans 24.54m
- Life : 100 years;
- Design Load : HL93, accounting with alone heavy means XB-80, pedestrian load 300KG/m2;
- Transaction bridge : 9m (car lane: 7m, balcony 2x0.5m, safety zone: 2x0.5m);
- Linking road transaction : road surface 8m long + strengthened border 2x1.0=2m;
- Earthquake load: Level 5;
Duration: 24 months
Contract Value : ……billion VND